NEW QUESTION # 60
In which workshop does planning for the next stage occur?

  • A. Team planning workshop
  • B. Progress review workshop
  • C. Release planning workshop
  • D. Team retrospective workshop

Answer: C

Explanation:
The Release Planning Workshop is the forum where planning for the next stage occurs in PRINCE2 Agile. This workshop brings together the project management team and delivery teams to plan the scope, schedule, and resources for the upcoming release or stage. It helps align business priorities with delivery capacity and supports incremental and iterative delivery approaches.
The Team Planning Workshop focuses on more detailed planning at the team level within the release, the Team Retrospective Workshop is dedicated to reflecting on performance and improving processes, and the Progress Review Workshop is for reviewing progress against the plan rather than planning future work.


NEW QUESTION # 61
Which of the following is a challenge when merging project management and agile?

  • A. Lack of guidance on doing agile
  • B. No clear processes to follow
  • C. Lack of guidance at delivery level
  • D. No common ground in terminology

Answer: A

Explanation:
One of the significant challenges when merging traditional project management approaches like PRINCE2 with agile delivery methods is the lack of guidance on doing agile. While PRINCE2 provides a structured framework focusing on governance, control, and business justification, agile introduces flexible, iterative, and people-centered approaches. The integration of these requires clear guidance on how to implement agile practices effectively within the PRINCE2 framework.
PRINCE2 Agile acknowledges that while it offers a comprehensive method to combine governance and agility, many organizations and practitioners struggle with practical implementation, especially in how to "do agile" properly. This includes understanding how to adopt agile roles, ceremonies, and artifacts without losing control, as well as aligning agile delivery with PRINCE2's management layers.
The challenge is compounded by the fact that agile methodologies emphasize adaptive planning and team autonomy, whereas traditional project management often focuses on upfront planning and command-and- control structures. PRINCE2 Agile aims to bridge this gap by providing detailed guidance, but a lack of practical 'how-to' agile advice remains a common issue.
Other options like terminology differences (A), unclear processes (B), and guidance at delivery level (C) are lesser challenges because PRINCE2 Agile provides a common vocabulary and defined processes that include delivery considerations.
Reference: PRINCE2 Agile Foundation Version 2, Section 1.4 "Challenges of Combining Agile and PRINCE2," and PRINCE2 Agile Study Guide, Chapter 1.


NEW QUESTION # 62
What information is NOT typically displayed on a burn chart?

  • A. Amount of time elapsed
  • B. Effort remaining
  • C. Team working agreements
  • D. Actual amount of work done

Answer: C


NEW QUESTION # 63
What term is used to describe boards that display what work needs to be completed for people working on a project?

  • A. Work in progress limit
  • B. Highlight report
  • C. Glad! Sad! Mad!
  • D. Information radiator

Answer: B


NEW QUESTION # 64
Which statement about velocity is CORRECT?

  • A. It is shown by the ideal line on a bum-down chart
  • B. It tracks the time and cost of a timebox
  • C. It describes how much work is getting done
  • D. It is based on the concept of rationalism

Answer: C


NEW QUESTION # 65
What is the purpose of the 'agile enablement' workshop?

  • A. To identify, assess, and plan for risks associated with project delivery
  • B. To identify, assess, and plan for risks associated with business as usual
  • C. To identify, assess, and plan for risks associated with agile adoption
  • D. To identify, assess, and plan for risks associated with transitioning products into operations

Answer: C

Explanation:
The Agile Enablement Workshop is specifically designed to support the transition of teams and organizations into agile ways of working. Its primary purpose is to identify, assess, and plan for risks related to agile adoption. This includes challenges like cultural resistance, skills gaps, tooling needs, and process adaptations.
The workshop ensures that these risks are proactively managed to smooth the agile transformation and increase the chances of successful agile delivery.
By focusing on agile adoption risks rather than project delivery or business as usual, the workshop addresses the foundational changes required for agility at team and organizational levels. Effective enablement workshops facilitate buy-in, identify training needs, and help tailor agile frameworks to the organization's context.
Reference: PRINCE2 Agile Foundation Version 2, Section 4.4 "Agile Enablement," and PRINCE2 Agile Study Guide, Chapter 4.


NEW QUESTION # 66
Which role is responsible for facilitating the Agilometer assessment?

  • A. Team manager
  • B. Project board
  • C. Customer subject matter expert
  • D. Project manager

Answer: D


NEW QUESTION # 67
In Lean Startup, what is based on the concept of 'learn the most with the least effort'?

  • A. A measurement of lead times
  • B. A minimum viable product
  • C. A set of criteria to determine whether work can be started
  • D. A structured, timeboxed event

Answer: B


NEW QUESTION # 68
Which is a purpose of the 'controlling stage' process?

  • A. To establish whether the project is complete
  • B. To report stage progress to the project board
  • C. To draft the plan for the next stage's work
  • D. To execute and deliver the project product

Answer: B

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


NEW QUESTION # 69
Which of the following defines agility?

  • A. The ability to embrace and respond to change
  • B. The core belief that anyone is capable of learning
  • C. The ability to protect from uncontrolled changes
  • D. The set of activities that define the sequence of actions

Answer: A

Explanation:
Agility is defined as the ability to embrace and respond to change quickly and effectively. It is a core principle of agile methods, enabling organizations and teams to adapt to evolving business needs, customer feedback, and external factors while delivering value continuously.
This definition contrasts with traditional change control, which often aims to prevent changes (C). Agility promotes flexibility, learning, and continuous improvement, but the belief that anyone is capable of learning (D), while important, is a cultural aspect rather than a direct definition of agility. The sequence of actions (A) relates more to processes than agility itself.
Understanding agility as the capacity to adapt ensures project approaches remain relevant in dynamic environments.
Reference: PRINCE2 Agile Foundation Version 2, Section 2.1 "What Is Agility?", and PRINCE2 Agile Study Guide, Chapter 2.


NEW QUESTION # 70
Which practice has the purpose of defining the products to be delivered, and who will deliver them?

  • A. Business case
  • B. Risk
  • C. Plans
  • D. Organization

Answer: D

Explanation:
Agile Foundation guidance, aligned with PRINCE2 and PRINCE2 Agile practices, explains that the organization practice is responsible for defining the products to be delivered and clarifying who will deliver them. This makes option C the correct answer. The organization practice focuses on establishing and maintaining a clear project management team structure, roles, responsibilities, and relationships to ensure effective delivery.
A key purpose of the organization practice is to ensure that accountability for producing each product is clearly defined. This includes identifying roles such as project manager, product owner, team members, and supporting roles, and ensuring that everyone understands what they are responsible for delivering. By defining who is involved and how they interact, the organization practice creates the foundation for collaboration, decision-making, and governance.
Option A, plans, focuses on when and how work will be carried out rather than who will deliver specific products. Planning answers questions about timelines, sequencing, and dependencies but assumes that responsibilities are already defined. Option B, the business case, explains why the project is worthwhile by outlining expected benefits, costs, and risks, not who will deliver products. Option D, risk, addresses uncertainty and potential threats or opportunities, not product ownership or delivery responsibility.
Agile Foundation documents emphasize that clarity of roles and responsibilities is especially important in Agile environments, where teams are empowered and self-organizing. The organization practice supports this empowerment by setting clear boundaries and accountability while avoiding unnecessary hierarchy. It ensures that everyone involved understands their contribution to value delivery and how their work fits into the wider project.
By defining both the products to be delivered and who will deliver them, the organization practice supports transparency, effective collaboration, and confidence among stakeholders. This clarity enables Agile teams to work autonomously within agreed structures, supporting consistent, high-quality delivery aligned with Agile and PRINCE2 Agile principles.


NEW QUESTION # 71
Which workshop reflects on lessons learned?

  • A. Team planning workshop
  • B. Agile enablement workshop
  • C. Project kickoff workshop
  • D. Project closure workshop

Answer: D

Explanation:
The Project Closure Workshop is the formal forum used to reflect on lessons learned during the project lifecycle. It is held towards the end of the project and provides an opportunity for the project team, stakeholders, and sponsors to review successes, challenges, and areas for improvement.
Capturing lessons learned supports organizational learning, helps avoid repeating mistakes, and improves future projects and agile adoption. This reflective practice aligns with PRINCE2's focus on continuous improvement and governance requirements.
Other workshops such as team planning (A) focus on upcoming work, agile enablement (B) on agile adoption, and project kickoff (C) on project initiation, none of which prioritize lessons learned reflection.
The project closure workshop is a vital practice to ensure knowledge retention and maturity in both traditional and agile project environments.


NEW QUESTION # 72
Which of the following describes co-creation?

  • A. Instructing the execution of tasks
  • B. Agreeing ways of working to ensure they are adopted
  • C. Shared attitudes, values, and goals
  • D. Motivating people to make sure they meet objectives

Answer: C

Explanation:
Agile Foundation guidance describes co-creation as a collaborative approach where value is created together by people who share common attitudes, values, and goals. This makes option C the correct answer. Co-creation goes beyond simply assigning work or motivating individuals to meet predefined objectives. Instead, it emphasizes collective ownership, shared understanding, and active participation by all relevant stakeholders in shaping outcomes.
In Agile environments, co-creation is rooted in the belief that the best solutions emerge when diverse perspectives work together in an open and trusting environment. Teams, customers, users, and stakeholders collaborate continuously to explore needs, generate ideas, and refine solutions. This shared mindset ensures that everyone involved is aligned on purpose and value, rather than working in isolation or following instructions without context.
Option A focuses on motivation to meet objectives, which reflects performance management rather than co-creation. While motivation is important, it does not necessarily involve shared ownership or joint value creation. Option B, agreeing ways of working, relates to establishing working agreements or team norms, which support collaboration but do not define co-creation itself. Option D, instructing the execution of tasks, represents a command-and-control approach that is contrary to Agile principles and does not encourage shared responsibility or creativity.
Agile Foundation documents emphasize that co-creation strengthens engagement, trust, and innovation. When people share attitudes, values, and goals, they are more likely to challenge assumptions constructively, learn from each other, and adapt solutions based on feedback. This approach supports Agile principles such as collaboration, customer focus, and continuous improvement. Co-creation ensures that value is not simply delivered to stakeholders but created with them, leading to better outcomes, higher satisfaction, and more sustainable Agile ways of working.


NEW QUESTION # 73
Which technique is used in the 'Issues' practice?

  • A. Refactoring
  • B. Trading/swapping
  • C. Objectives and key results
  • D. Delegation poker

Answer: B

Explanation:
Trading/swapping is a technique used within the issues practice to manage and resolve conflicts or competing priorities by negotiating trade-offs. For example, scope items, resources, or deadlines may be traded or swapped between stakeholders to reach agreements that keep the project on track.
This collaborative negotiation supports flexible, pragmatic issue resolution, aligning with agile values of collaboration and customer focus. It enables project teams to balance competing demands while maintaining progress and business justification.
Objectives and key results (B) are goal-setting tools, refactoring (C) is a technical practice for code improvement, and delegation poker (D) is about decision-making authority - none specifically target issue resolution.
Trading/swapping aligns with PRINCE2's controlled management of issues and agile's collaborative problem-solving approach.


NEW QUESTION # 74
Which statement about the 'embrace change' target is CORRECT?

  • A. It reduces the planning of dependencies between projects
  • B. It reduces testing in order to meet deadlines
  • C. It encourages the customer to raise new ideas
  • D. It minimizes the time needed to train a new team member

Answer: C

Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?
showNav=true&expandNav=true&page=PRA_41


NEW QUESTION # 75
In which workshop are the project role descriptions created?

  • A. Project initiation workshop
  • B. Starting-up workshop
  • C. Project kickoff workshop
  • D. Project canvas workshop

Answer: B

Explanation:
The starting-up workshop is the initial workshop where the foundation for the project is established, including the creation and clarification of project role descriptions. Defining roles early ensures clarity of responsibilities, helps establish governance, and sets expectations for the project team.
Kickoff (B) focuses on launching the project, initiation (C) develops detailed plans, and the project canvas (D) is a tool for capturing high-level information but does not define roles explicitly.
Reference: PRINCE2 Agile Foundation Version 2, Section 4.5 "Starting Up a Project," and PRINCE2 Agile Study Guide, Chapter 4.


NEW QUESTION # 76
......