Free renewal for a year
In order to keep abreast of the times, our company will continuously update our Oracle EBS R12: Advanced Supply Chain Planning vce exam dumps. And after payment, you will automatically become the VIP of our company. Therefore you will get the privilege to enjoy free renewal of our 1z1-244 valid study vce during the whole year. No matter when we have compiled a new version of our 1z1-244 : Oracle EBS R12: Advanced Supply Chain Planning Pass4sures training dumps, our operation system will automatically send the latest version of the study materials for the exam to your email, all you need to do is just check your email then download 1z1-244 pdf vce collection. All of the staffs in our company wish you early success.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Practice test provided by the software version
There is no denying that practice test means a lot for those candidates who are preparing for an exam. Our company has taken the importance of Oracle EBS R12: Advanced Supply Chain Planning latest Pass4sures questions for workers in to consideration, so we will provide mock exam for our customers in software version. On the one hand, the workers can have access to accumulate experience of Oracle Applications Oracle EBS R12: Advanced Supply Chain Planning valid study vce in the practice test, which is meaningful for them to improve their knowledge as well as relieving stresses. On the other hand, the workers can increase their speed and the standardization for answering the questions in the 1z1-244 pdf vce collection.
Free demo before buying
Just like the old saying goes "True gold fears no fire; a person of integrity can stand severe tests." We are totally believe that our Oracle Oracle EBS R12: Advanced Supply Chain Planning Pass4sures training dumps are the most useful and effective study materials in the field, and that is why we would like to provide free demo in our website for you to have a try. The free demo is a part of our real Oracle EBS R12: Advanced Supply Chain Planning latest Pass4sures questions, and in the demo you will have access to get a rough idea of our Oracle EBS R12: Advanced Supply Chain Planning valid study vce, what's more, you will be able to get to know what it is look like after opening the software as well as the usage of our software. Please feel free to click the download free Oracle EBS R12: Advanced Supply Chain Planning Pass4sures training dumps in our website, we are look forward to help you in the course of preparing for the exam
It is an inevitable fact that a majority of people would feel nervous before the important exam (Oracle EBS R12: Advanced Supply Chain Planning latest Pass4sures torrent), as for workers, the exam is one of the most essential exams in their career, so how to reduce pressure for the candidates of the exam has become an urgent problem for the workers. Now, here comes a piece of good news, our Oracle Applications 1z1-244 pdf vce collection will be of great importance for you in the process of preparing for the actual exam. Our company has consistently hammered at compiling the most useful and effective study materials for workers, and the Oracle Oracle EBS R12: Advanced Supply Chain Planning vce exam dumps are the fruits of the common efforts of our top experts who are coming from many different countries. There are numerous shining points of our Oracle Applications Oracle EBS R12: Advanced Supply Chain Planning valid study vce, such as free demo before buying, practice test provided by the software version, free renewal for a year to name but a few.
Oracle 1z1-244 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Planning Fundamentals & Architecture | 15% | - Planning Data Collection & Setup - ASCP Architecture & Planning Methods - ASCP Overview & Key Capabilities |
| Optimization & Advanced Features | 15% | - Cost-Based Optimized Plans - Alternate Resources, BOMs, and Substitutions - Penalty Factors and Optimization Parameters |
| Modeling the Supply Chain | 20% | - Lead Times and Supply Chain Structure - Bills of Material and Routings - Organizations, Items, and Calendars - Resources, Sourcing Rules, and Assignment Sets |
| Constrained Planning | 20% | - Enforcing Capacity and Material Constraints - Analyzing Late Demand and Supply Issues - Decision Rules and Constraints Configuration |
| Unconstrained Planning | 15% | - Exceptions and Recommendations - Creating and Running Unconstrained Plans - Planner Workbench Navigation |
| Plan Analysis, ATP & Execution | 15% | - Releasing Planned Orders - Key Performance Indicators & Metrics - Pegging, Supply/Demand Review - Available-to-Promise (ATP) Functionality |
Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
1. You are using a Material and Resource Constrained Plan. Your horizon Is the near term future.
Identify the correct question or goal for this plan.
A) Generate a feasible plan that respects material, resource, distribution, and transportation constraints.
B) Generate an optimized and executable plan based on plan objectives and material, resource, and transportation constraints.
C) How much resource capacity would I need to arrange to satisfy all anticipated demand in a timely manner?
D) How much material availability would I need to arrange to satisfy all anticipated demand in a timely manner?
E) How much resource capacity and material availability would I need to arrange to satisfy all anticipated demand in a timely manner?
2. Which two actions offer a possible resolution to the exception message "Past due forecast"?
A) revising the Forecast Due Date to a date later than the Demand Satisfied Date
B) revising the Forecast Due Date to a date later than the Plan Horizon Start Date
C) revising the Demand Priority Rules
D) deleting the Forecast entry
E) increasing Demand Priority of the Forecast entry
3. Identify the correct statement about setting lead time information In the Sublnventory Definition form.
A) The precedence for lead time Is Items (First priority), Supplier (Second priority), and Subinventory (Third priority).
B) The ASCP planning engine uses the sublnventory lead time Information only for an Intra-Organization transfer purpose.
C) The ASCP Planning engine does not use the lead times defined in the Sublnventory Definition form.
This Is only for the Min-Max Planning process.
D) The ASCP planning engine uses Preprocessing and Postprocessing lead times only from the Sublnventory Definition form.
E) The lead times defined in the Subinventory Definition form is used only during a Constrained Optimized plan with penalty factors and decision rules.
F) The ASCP planning engine uses the subinventory lead time information only for transfers across Organizations.
4. Your client Is currently using a Constrained Plan In Production. The client states that the Inventory Turn Index remains below Its target and feels that an optimized plan would allow them to Improve their Inventory turns.
You Instruct the client that there are some additional setups required for the Optimized Plan to give meaningful results.
Identify the three setups that you would recommend as the minimum for an Optimized Plan to give credible results.
A) Exception Templates
B) Profile option MSO: Inventory Carrying costs
C) Inter-Organization Transfer Charge
D) Plan level Penalty factors
E) Penalty cost factor for exceeding Transportation Capacity at Ship Method Level
F) Rolled up manufactured Item cost
5. End Item A can be substituted with End Item B and End Item B can be substituted with End Item
C. The effective dates for these substitutions are given in the Exhibit.
Which three statements are correct?
A) End Item A substitution with End Item C is not possible.
B) The inferred substitution rule between Item A and C is effective only from 06-JAN-2008 to 10- JAN-2008.
C) Plan your entire horizon in daily buckets to improve performance.
D) Plan Individual Resources In the short term and aggregate Resources in the longer term buckets.
E) If End Item A is requested, it can be satisfied with the supplies from End Items A or B or C.
You anticipate having a very large plan with many Items, Purchase Orders, and Sales Orders.
You want to plan at a detailed Item level as much as possible, but detailed Resource planning Is less Important.
Because your enterprise Is global. It Is Important to have the plan run In the shortest possible time.
Identify two aggregation settings that will help you achieve your goals.
F) End Item A substitution with End Item C Is Inferred.
G) The inferred substitution rule between Item A and C is effective from 06-JAN-2008 to 22- JAN-2008.
H) Plan at the Item level In the short range and Product Family level in the long range.
I) Plan your entire horizon in weekly buckets.
Solutions:
| Question # 1 Answer: E | Question # 2 Answer: A,E | Question # 3 Answer: B | Question # 4 Answer: D,E,F | Question # 5 Answer: A,G |