- Agile Principles and Mindset 16%
- Continuous Improvement (Product, Process, People) 9%
- Team Performance 16%
- Problem Detection and Resolution 10%
- Adaptive Planning 12%
- Stakeholder Engagement 17%
NEW QUESTION 87
What is the best definition of "Done"?
- A. The prodct has passed QA and has all of the required release documentation
- B. It is determined by the Scrum Master
- C. The definition of "Done" is one that would allow the development work to be ready for a release.
- D. Whatever will please the Product Owner
Answer: C
NEW QUESTION 88
A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process. The project manager's initial plan should be to:
- A. Institute daily standup meetings immediately.
- B. Balance teaching principles with Agile practices.
- C. Rate the team's progress in learning new methods.
- D. Communicate the Agile Manifesto to the team.
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 89
A change made to the internal structure of software that makes it easier to understand and cheaper to modify but does not change its observable behavior is referred to as:
- A. Refactoring
- B. A Spike
- C. A User Story
- D. Technical debt
Answer: A
NEW QUESTION 90
Which best describes the attributes of the IN VEST criteria in a user story?
- A. Innovation, Nested, Vision, Estimating, Scalable, and Team
- B. Incremental, Net, Variation, Exceed, Scope, and Training
- C. Interdependent, Nonfunctional, Value, Exploratory, Sprint, and Timebox
- D. Independent, Negotiable, Valuable, Estimable, Small, and Testable
Answer: D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 91
Who is responsible for prioritizing the stories that will be included in the iteration?
- A. Team
- B. ScrumMaster
- C. Product Owner
- D. Developer
Answer: C
NEW QUESTION 92
What role should a servant leader perform to reduce team distractions and improve progress toward project goals?
- A. Managing: To ensure compliance with the project plan
- B. Mentoring: To share their knowledge with the team
- C. Auditing: To ensure adherence to organizational compliance policies
- D. Controlling: To ensure compliance with the scope, budget, and schedule
Answer: B
NEW QUESTION 93
On an agile project some of the development team is struggling to understand how the tasks and use stones fit into the overall product. How should this be addressed?
- A. Create a story map for the minimal viable product (MVP) functionality
- B. Review the iteration goals and have the team each describe the work to create shared understanding
- C. Have the product owner explain the product vision and review the release plan with the team
- D. Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session.
Answer: C
NEW QUESTION 94
A "Scrum of Scrums" meeting is:
- A. Another name for the daily standup project meeting in a Scrum team.
- B. Amechanism that coordinates multiple teams working on a single project.
- C. Aproject meeting that happens twice every day across the Scrum teams.
- D. An occasional leadership meeting that provides direction to multiple Scrum teams.
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION 95
A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company.
What should the agile coach ensure that developers do?
- A. Establish pair programming partners, and regularly perform peer reviews.
- B. Send coding to the quality assurance (QA) team upon completion.
- C. Demonstrate each feature to the client as soon as coding is complete.
- D. Perform demos at the end of each iteration.
Answer: D
NEW QUESTION 96
According to DeMarco, Fragmented knowledge workers may look busy but a lot of their business is just thrashing. The minimum cost penalty is :
- A. 10%
- B. 15%
- C. 25%
- D. 5%
Answer: B
NEW QUESTION 97
In a Lean project environment, visual controls:
- A. Should be kept to a minimum to avoid distracting the team from high-value activities.
- B. Are helpful while the team is forming but are less important for more experienced teams.
- C. Are easy to use, reflect the team's progress, and show the team what to do next.
- D. Can be used by management for communicating specific corrective direction.
Answer: D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 98
Highly visible project displays are called:
- A. Information refrigerators
- B. Project distributors
- C. Information radiators
- D. Project radiators
Answer: C
NEW QUESTION 99
Who is responsible for prioritizing the stories that will be included in the iteration?
- A. Team
- B. ScrumMaster
- C. Product Owner
- D. Developer
Answer: C
NEW QUESTION 100
In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?
- A. Sprint Retrospective
- B. Sprint planning
- C. Daily Scrum
- D. Release planning
Answer: A
NEW QUESTION 101
Who is responsible for ordering the Product Backlog?
- A. The Development Team
- B. The Scrum Master
- C. The Product Owner
- D. Senior Executives
Answer: C
NEW QUESTION 102
Sprints lengths can vary each Sprint as long as they don't exceed a month.
- A. True
- B. False
Answer: A
NEW QUESTION 103
During the daily standup meeting, a team member states that an issue has been encountered. This leads to the team members getting into a problem-solving discussion. How should the ScrumMaster respond?
- A. Abruptly end the daily standup meeting and schedule another meeting to discuss the issue.
- B. Ask the team members to table the discussion until after the meeting is over.
- C. If the item is really important, allow the discussion to expedite resolution of the issue.
- D. Ask the team how they would like to use the daily standup meeting for that day.
Answer: B
NEW QUESTION 104
Frequent verification and validation is key in Agile but each approach produces a very different result. Verification determines ________________ whereas validation determines _____________.
- A. if the product is "done" | if the product is "done-done"
- B. if I am I building the product right | if I am I building the right product
- C. if I am I building the right product | if I am I building the product right
- D. if the product has passed unit testing | if the product has passed acceptance testing
Answer: B
NEW QUESTION 105
......
PMI Agile Certified Practitioner PMI-ACP Exam
PMI Agile Certified Practitioner PMI-ACP Exam which is related to PMI-Agile Certified Practitioner Certification. This exam validates the ability to explore embrace and apply agile principles and mindset within the context of the project team and organization promote collaboration and participation throughout the project lifecycle and provide the tools for informed and effective decision making. It also deals with the ability to create an environment of trust learning, collaboration and conflict resolution that promotes the south organization and select, and tailor team process based on organizational characteristics and project as well as team experience in order to optimize value delivery. Project Managers, Members of the project team and Agile Project Professionals usually hold or pursue this certification and you can expect the same job role after completion of this certification.
Latest 2021 Realistic Verified PMI-ACP Dumps: https://www.pass4suresvce.com/PMI-ACP-pass4sure-vce-dumps.html
Pass Your PMI PMI-ACP Exam with Correct 210 Questions and Answers: https://drive.google.com/open?id=1E0AYalmgkvbxoHfUe6e8GhpkpvCHz76t