[Sep-2021] Verified PRINCE2 Exam Dumps with PRINCE2-Foundation Exam Study Guide [Q141-Q163]

Share

[Sep-2021] Verified PRINCE2 Exam Dumps with PRINCE2-Foundation Exam Study Guide

Best Quality PRINCE2 PRINCE2-Foundation Exam Questions Pass4suresVCE Realistic Practice Exams [2021]

NEW QUESTION 141
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.

  • A. any type of project
  • B. business as usual
  • C. programmes and projects
  • D. all types of programmes

Answer: A

 

NEW QUESTION 142
In which product would you find a product's quality tolerance defined?

  • A. Quality Management Strategy
  • B. Product Description
  • C. Quality Register
  • D. Configuration Item Record

Answer: B

 

NEW QUESTION 143
Which is an objective of the Directing a Project process?

  • A. Define how risks, issues and changes will be managed
  • B. Review and approve a project mandate
  • C. Ensure corporate or programme management has an interface to the project
  • D. Obtain approval for completed products

Answer: C

 

NEW QUESTION 144
Which is performed as part of the recommended risk management procedure?

  • A. Review of risk management practices to ensure that they are performed effectively
  • B. Allocation of a budget to investigate issues facing the project
  • C. Sending of information about risks tothe project to project stakeholders
  • D. Resolution of conflicts between the project and the programme board

Answer: C

 

NEW QUESTION 145
Which is a minimum requirement for applying the organization theme?

  • A. To include external stakeholders on the project board
  • B. To define the experience required for each project role
  • C. To train project team members in the use of PRINCE2
  • D. To document the project management team structure

Answer: D

Explanation:
Explanation
Reference http://prince2.wiki/Themes#Organization_Theme

 

NEW QUESTION 146
Which statement about the quality review technique is FALSE?

  • A. It enables a check to be made on a product's fitness for purpose
  • B. It is used to gain wider acceptance of a product by involving key interested parties
  • C. It defines the quality responsibilities of the project team
  • D. It supports the management of future changes by providing abaseline for a product

Answer: C

 

NEW QUESTION 147
Which process covers the work done by external suppliers who may NOT be using PRINCE2?

  • A. Closing a Project
  • B. Managing a Stage Boundary
  • C. Managing Product Delivery
  • D. Directing a Project

Answer: C

 

NEW QUESTION 148
Which is one of the six aspects of project performance that needs to be managed?

  • A. Risk
  • B. Security
  • C. Progress
  • D. Change

Answer: A

Explanation:
Section: Volume A

 

NEW QUESTION 149
Which is a responsibility of a risk owner?

  • A. Manage, monitor and control all aspects of an assigned risk
  • B. Own and authorize theuse of the risk budget to fund risk responses
  • C. Identify risks to the project that might occur in their department
  • D. Determine project risk appetite

Answer: A

 

NEW QUESTION 150
Which is a benefit of using PRINCE2?

  • A. It enables a project manager to be accountable for the success of a project
  • B. It includes techniques for critical path analysis and earned value analysis
  • C. It prevents any changes once the scope of a project has been agreed
  • D. It promotes consistency of project work and the ability to reuse project assets.

Answer: D

 

NEW QUESTION 151
Which is a purpose of the Quality theme?

  • A. Establish how the project will ensure that all products created meet their requirements
  • B. Identify all the products of the project to ensure the scope has been adequately defined
  • C. Determine the communication needs of the organization's quality assurance function
  • D. Establish quality assurance to maintain the quality management system

Answer: A

 

NEW QUESTION 152
Which is part of quality control?

  • A. Writing product descriptions
  • B. Providing assurance that the project is being conducted properly
  • C. Undertaking quality reviews
  • D. Documenting the customer's quality expectations

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#Part_2:_Quality_Control_Introduction

 

NEW QUESTION 153
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

  • A. Project Plan
  • B. Team Plan
  • C. Benefits Review Plan
  • D. Stage Plan

Answer: D

 

NEW QUESTION 154
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

  • A. Only corporate or programme management
  • B. Only the Project Manager
  • C. All levels of management
  • D. Only the Project Board

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 155
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

  • A. Estimations of the likelihood and impact of risks
  • B. A description of the risk management procedure
  • C. An explanation of the company's risk appetite
  • D. The names of the assigned actionees for each risk

Answer: B

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/

 

NEW QUESTION 156
Which describes a risk event?

  • A. The sequence of events and actions that will be put in place if a risk occurs
  • B. The area of uncertainty in terms of the threat or opportunity
  • C. The achievement of a milestone on the project plan
  • D. The derivation or sources of a potential risk to the project

Answer: B

Explanation:
Explanation
Reference http://prince2.wiki/Risk

 

NEW QUESTION 157
Which statement about stages is true?

  • A. The use of management stages is mandatory
  • B. The use of technical stages is mandatory
  • C. Management stages should be of the same duration
  • D. Management stages are driven by specialist teams

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 158
Which is NOT considered when defining risk tolerance?

  • A. A Project Board's attitude towards risk taking
  • B. An organization's risk appetite
  • C. The allocated risk budget
  • D. The amount of risk a Project Board considers acceptable

Answer: C

 

NEW QUESTION 159
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.

  • A. themes
  • B. tolerances
  • C. principles
  • D. processes

Answer: B

 

NEW QUESTION 160
What is the result of the change derived from using the project's product?

  • A. Dis-benefit
  • B. Benefit
  • C. Output
  • D. Outcome

Answer: D

 

NEW QUESTION 161
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

  • A. stage cost tolerance
  • B. product cost tolerance
  • C. Work Package cost tolerance
  • D. project cost tolerance

Answer: C

 

NEW QUESTION 162
Which is a purpose of a Risk Register?

  • A. Capture risks that may occur during the project
  • B. Record the risk tolerance for the project
  • C. Record how risk management activities will be undertaken on the project
  • D. Capture issues which are impacting on the delivery of the project objectives

Answer: A

 

NEW QUESTION 163
......

Authentic Best resources for PRINCE2-Foundation: https://www.pass4suresvce.com/PRINCE2-Foundation-pass4sure-vce-dumps.html

PRINCE2-Foundation Test Engine Practice Exam: https://drive.google.com/open?id=1LLc-2f5tzwoNOtih_yjE53S67VR_qAQ-